Overview
Most parts of Hong Kong have a reasonable
degree of flood protection. However, serious flooding had occurred on
the natural flood plains and low-lying areas of the northern part of the
NT. Flooding is also a recurring problem in the older urban areas, like
West Kowloon, because of the inadequacy of the drainage system
constructed long ago.
To mitigate the problem, DSD has been
implementing a massive $10 billion flood prevention programme of river
training works and village flood pumping schemes in the NT, and a $3.7
billion programme of urban drainage improvement works in West Kowloon so
as to raise the flood protection standards substantially. Since 1997,
about 55km of rivers in the northern parts of NT have been trained with
24 village flood pumping schemes in operation, bringing relief to the
flooding situation in NNT and NWNT. Since 1995, we have removed 82
flooding black spots in both the urban and rural areas.
Flooding Incidents in 2004/05
In 2004, the annual rainfall depth was around
1,739 mm, lower than the average of 2,214 mm by about 21%. The Amber
Rainstorm Warning Signal was hoisted 16 times. Red and Black Rainstorm
Warning Signals were only hoisted in the morning on 8.5.2004 - all
attributable to the same rainfall event, which mainly affected the
western part of the Kowloon Peninsula. Flooding was reported at
low-lying areas in Mong Kok and Sham Shui Po where the relevant flood
prevention works under the West Kowloon Drainage Improvement Project had
not yet been completed. There was no major flooding event in other
areas.
Nevertheless, the flooding problem at West Kowloon has been
progressively improved since the substantial completion of the Stages 1
and 2 works in 2003 and 2004 respectively. In particular, the completion
of the Tai Hang Tung Storage Scheme and Kai Tak Transfer Scheme in end
2004 has denoted a significant achievement of the department in
alleviating the flooding problem of West Kowloon.
Progress made in 2004-05
Flood prevention projects with a total project
cost of about $2 billion have been substantially completed, signifying
the overall completion of a village flood pumping scheme at Wang Chau,
2.3 km of new drainage channels in Ngau Tam Mei, 23 km of stormwater
drains in West Kowloon, a 100,000 m3 flood storage tank at Tai Hang Tung and 1.42 km of drainage tunnel from Waterloo Road to Kai Tak Nullah.
To further improve the flooding situation, the Government is
actively implementing a series of major drainage improvement works that
aim at providing Hong Kong with a high degree of flood protection.
Construction works costing about $2.2 billion and $0.7 billion are being
carried out in the NT and West Kowloon respectively. A further $6.3
billion of drainage improvement projects is also under planning or
design for the NT, West Kowloon and other flood prone areas such as East
Kowloon, Tsuen Wan, Northern Hong Kong Island. All major flood control
projects are listed in Appendix A, whereas locations of the projects are shown in Appendix B.
Reduce Flooding Black Spots
Since 1994, DSD has identified more than a
hundred flooding black spots. All of the black spots are under close
surveillance and improvement measures have been taken to eradicate or
reduce the flood risk. Last year, we have successfully removed 10
flooding black spots.
Flood Prevention in the Urban Areas
Flood prevention projects in the urban areas
mainly include improvements of the stormwater drainage networks in order
that stormwater would be collected and conveyed efficiently. Under some
special circumstances, innovative methods such as flood storage, flood
pumping or flow diversion are used to minimize the extent of works that
may cause disturbances to traffic or conflict with underground
utilities.
In West Kowloon, works under Stages 1 and 2 of the West Kowloon
Drainage Improvement Project were completed in June 2003 and December
2004 respectively. These included about 33 km of stormwater drains in
Yau Ma Tei, Mong Kok, Kowloon Tong, Sham Shui Po and Lai Chi Kok, as
well as an underground flood storage tank in Tai Hang Tung and a
stormwater diversion tunnel from Kowloon Tong to Kai Tak Nullah. Under
Stage 3, the construction of about 12 km of stormwater drains is in
progress for completion in 2007. Plan is also in hand to implement a
stormwater transfer scheme at Lai Chi Kok, as this area is susceptible
to flood risk due to surface runoff from the hinterland and the
potential overflow from the Kowloon group of reservoirs.
For flood prone areas in the Northern Hong Kong Island and East
Kowloon, drainage improvement projects costing about $2.6 billion are
being planned. In order to minimize the disturbance to local residents
and road traffic caused by trench excavation, stormwater drainage
tunnels will be constructed to divert stormwater away from mid-level so
as to reduce the loading on the existing urban drainage systems which
are under capacity.
Flood Prevention in NT
Flood prevention projects in the NT can
broadly be classified into two main types, namely drainage channels to
collect and convey floodwater to the sea and village flood pumping
schemes to protect villages in low-lying areas.
With the completion of several drainage channels in recent years,
the flooding situation in the NT has been significantly improved,
particularly in Lo Wu, Ho Sheung Heung, Yin Kong and Tin Ping Shan in
the Northern NT and Tin Shui Wai, Yuen Long and Kam Tin in the
Northwestern NT. In the past, floodplains in the NT were often
susceptible to flooding to 1 to 1.5 m depth as overflow took place along
the old river sections which were narrow and sinuous. Nowadays, tens of
thousands of people in these flood prone areas have been relieved of
flooding risks.
As regards low-lying villages in the flood
plain areas, we have already completed 24 village flood pumping schemes
to remove the flood risks at 31 low-lying villages. Over 240 hectares of
low-lying villages areas accommodating a population of 30,000 people
are now being protected.
In the Northern NT, the Stage 3 works of the Shenzhen River
Regulation Project and the Rehabilitation of River Ganges were in good
progress. With the completion of these two drainage improvement projects
in 2006, the flooding situation at Lo Shue Ling, the last regional
flooding black spot in the Northern NT, will be significantly improved.
In the Northwestern NT, construction works of the Yuen Long Bypass
Floodway and San Tin Eastern Main Drainage Channel, as well as three
village flood pumping schemes at Tai Kiu, Shui Pin Tsuen, and Mai Po Lo
Wai/Mai Po San Tsuen were progressing well.
Plan is also in hand to improve the stormwater
drainage systems in Tuen Mun, Sha Tin, Tai Po, Tsuen Wan, Sai Kung and
Lantau Island.
Better Preparation for the Rainy Days with New System
DSD has developed a Flood Monitoring and
Reporting System (FMRS) to monitor the flooding situation and to collect
the hydrological data for the calibration of computer drainage models.
Under the system, more than 60 automated gauging stations were installed
at rivers and channels throughout the territory. The gauging stations
provide real-time round-the-clock surveillance of water levels and to
collect hydrological data including rainfall depths and tide levels.
Most of these stations are equipped with ultrasonic probes to measure
water depths in rivers with great precision, and transmit the real-time
data immediately to DSD control center. Duty officers at the control
center could analyze the flooding situation based on the real-time
trends of hydrometric information, video images and operation status of
the gauging stations, and issue any necessary flood warnings to relevant
emergency services such as Police and Fire Services Department and the
drainage maintenance crews to mitigate the flood risk.
Through collaboration with the University of Hong Kong, DSD improved
the FMRS in 2002 by installing the Mobile and Online Surveillance and
Incident Controller II system for gathering and transmission of
hydrometric information based on wireless telemetry technology. This
system, which is a forerunner in the Asian-Pacific region, adopts the
advanced mobile communication technology called General Package Radio
Services to compress and transmit various data collected from the
gauging station to DSD control center in a speed 8 times faster than
common GSM mobile phones. To make use of renewable energy and to reduce
the installation and operation costs, many of the stations have been
powered by solar battery cells. Moreover, DSD has installed night vision
digital network cameras at some flooding black spots to provide
real-time high resolution images of the critical drainage locations. Due
to the application of these innovative technologies, the average
failure rate of the gauging stations during adverse weather conditions
was significantly reduced from 17.4% in 2001 to 4.6% in 2004.
Enlarge
Working with University to Solve Urban Flooding
The existing drains in the northern part of
Hong Kong Island from Tai Hang to Kennedy Town were generally built
decades ago. Areas like Connaught Road West, Des Voeux Road West,
Queensway, Hennessy Road, Morrison Hill Road, Happy Valley etc are
susceptible to flooding due to rapid developments and changes in land
use over the years. Substantial drainage improvement in the areas by
re-building or enlarging the existing drainage system will inevitably
require extensive excavation in busy roads and hence cause tremendous
nuisance to the public.
The design concept of the drainage tunnel is to intercept stormwater
by 36 water intakes located in the mid levels from Tai Hang to Kennedy
Town. Stormwater from the upper catchment intercepted by the intakes
will be directed into a deep tunnel and discharged at the western side
of Hong Kong Island. The lower catchment areas can thus be better
protected from flooding under heavy rainstorms.
Most of the proposed water intakes are located in congested build-up
areas. To ensure that the intakes can effectively collect huge volumes
of high speed flows during heavy rains, we engaged a consultant to
prepare the preliminary design for the vortex water intake structures
and the University of Hong Kong to carry out physical hydraulic model
test for verification purpose.
Flooding in Ngau Tam Mei Basin Becoming History
Ngau Tam Mei area is a low-lying areas in the
NT and has long been a well-known flooding black spot. Serious flooding
has occurred almost every year. The area has been classified as a major
flooding black spot (the most serious rank) according to DSD's
classification. Rapid development over the last 20 years has reduced the
flood storage capacity of the original flood plain and also increased
the volume of surface runoff that exacerbate the flooding problem.
To tackle the flooding problem, a new channel was designed to divert
the flood water from the upstream area of Ngau Tam Mei to the newly
constructed Kam Tin Channel directly. The channel is designed so that it
can accommodate the flow generated from a 200-year return period storm
event.
During low flow condition the water inside the channel was
comparatively small. The tidal water will back-flow from Kam Tin Channel
to the upstream area and thereby creating nuisance problem. As such, an
inflatable dam together with a low flow pumping station is provided at
the downstream end of the channel as a tidal barrier.
Construction of the channel started in late 1999 and completed in
March 2005. The flooding problem at Ngau Tam Mei areas is now resolved.
source:
ABOUT AUTHOR
Recent Posts
Trending
Categories
- ABC
- ajaib
- akik
- aktual
- aljazeera
- android
- Angrybirds
- antenna
- Apes
- artist
- AusAID
- australia
- Banjir
- Bank
- Batu
- bbm
- berita
- bir
- bisnis
- blokir
- Bola
- bridge
- budaya
- cnn
- computer
- Digital
- download
- edukatif
- Film
- font
- foto
- game
- hacking
- haji
- handphone
- health
- hiburan
- hidup
- hot
- humor
- ibu
- Indonesia
- inspirasi
- inspiratif
- internet
- iPad
- jakarta
- jalanan
- Jokowi
- Jujur
- kartini
- Kemdikbud
- Kereta Api
- kesehatan
- kliping
- Komputer
- Konferensi
- Korupsi
- kreatif
- kriminal
- Kuliner
- Kurikulum
- Kurikulum 2013
- lalu lintas
- lawas
- like
- lucu
- matematika
- media
- Memori
- menteri
- minimarket
- mobil
- motogp
- movie
- mts
- Mudik
- Musik
- Narkoba
- narsis
- nasib
- neraka
- news
- Olah raga
- otomotif
- Pahlawan
- pedati
- pemerintah
- pemuda
- pendidikan
- pesantren
- pesawat
- photo
- picture
- pilkada
- Polantas
- polisi
- pondok
- Presiden
- PSSI
- pulsa
- roaming
- rumah
- sawah
- SBMPTN
- sego kucing
- sejarah
- selular
- seni
- Sepak Bola
- setan
- Sholat
- simbol
- slip
- SMA
- smart
- sms
- snmptn 2013
- Solo
- spam
- streaming
- Subsidi
- surakarta
- surga
- Teknologi
- teroris
- TIK
- tilang
- time
- tip trik
- Tokoh
- tradisional
- Transportasi
- Trending Topic
- tutorial
- TV
- ubuntu
- UN
- video
- virus
- wajan
- Walikota
- wawancara
- windows 8
- wisata
- word
- youtube
Advertisement
Diberdayakan oleh Blogger.
Labels
ABC
ajaib
akik
aktual
aljazeera
android
Angrybirds
antenna
Apes
artist
AusAID
australia
Banjir
Bank
Batu
bbm
berita
bir
bisnis
blokir
Bola
bridge
budaya
cnn
computer
Digital
download
edukatif
facebook
Film
font
foto
game
google
hacking
haji
handphone
health
hiburan
hidup
hot
humor
ibu
Indonesia
inspirasi
inspiratif
internet
iPad
jakarta
jalanan
Jokowi
Jujur
kartini
Kemdikbud
Kereta Api
kesehatan
kliping
Komputer
Konferensi
Korupsi
kreatif
kriminal
Kuliner
Kurikulum
Kurikulum 2013
lalu lintas
lawas
like
lucu
matematika
media
Memori
menteri
minimarket
mobil
motogp
movie
mts
Mudik
Musik
Narkoba
narsis
nasib
neraka
news
Olah raga
otomotif
Pahlawan
pdf
pedati
pemerintah
pemuda
pendidikan
pesantren
pesawat
photo
picture
pilkada
Polantas
polisi
pondok
Presiden
PSSI
pulsa
roaming
rumah
sawah
SBMPTN
sego kucing
sejarah
selular
seni
Sepak Bola
setan
Sholat
simbol
slip
SMA
smart
sms
snmptn 2013
Solo
spam
streaming
Subsidi
surakarta
surga
Teknologi
teroris
TIK
tilang
time
tip trik
Tokoh
tradisional
Transportasi
Trending Topic
tutorial
TV
ubuntu
UN
video
virus
wajan
Walikota
wawancara
windows 8
wisata
word
youtube
Labels List Numbered
- ABC
- ajaib
- akik
- aktual
- aljazeera
- android
- Angrybirds
- antenna
- Apes
- artist
- AusAID
- australia
- Banjir
- Bank
- Batu
- bbm
- berita
- bir
- bisnis
- blokir
- Bola
- bridge
- budaya
- cnn
- computer
- Digital
- download
- edukatif
- Film
- font
- foto
- game
- hacking
- haji
- handphone
- health
- hiburan
- hidup
- hot
- humor
- ibu
- Indonesia
- inspirasi
- inspiratif
- internet
- iPad
- jakarta
- jalanan
- Jokowi
- Jujur
- kartini
- Kemdikbud
- Kereta Api
- kesehatan
- kliping
- Komputer
- Konferensi
- Korupsi
- kreatif
- kriminal
- Kuliner
- Kurikulum
- Kurikulum 2013
- lalu lintas
- lawas
- like
- lucu
- matematika
- media
- Memori
- menteri
- minimarket
- mobil
- motogp
- movie
- mts
- Mudik
- Musik
- Narkoba
- narsis
- nasib
- neraka
- news
- Olah raga
- otomotif
- Pahlawan
- pedati
- pemerintah
- pemuda
- pendidikan
- pesantren
- pesawat
- photo
- picture
- pilkada
- Polantas
- polisi
- pondok
- Presiden
- PSSI
- pulsa
- roaming
- rumah
- sawah
- SBMPTN
- sego kucing
- sejarah
- selular
- seni
- Sepak Bola
- setan
- Sholat
- simbol
- slip
- SMA
- smart
- sms
- snmptn 2013
- Solo
- spam
- streaming
- Subsidi
- surakarta
- surga
- Teknologi
- teroris
- TIK
- tilang
- time
- tip trik
- Tokoh
- tradisional
- Transportasi
- Trending Topic
- tutorial
- TV
- ubuntu
- UN
- video
- virus
- wajan
- Walikota
- wawancara
- windows 8
- wisata
- word
- youtube
Random Posts
Social Share
Recent comments
Most Trending
-
ICM Airport Technics has been awarded a tender by Heathrow Airport Ltd to install Self Service Bag Drop trial units at Heathrow Airport. A...
-
Saya lebih tertarik untuk membicarakan, siapa saja sih yang boleh jadi menteri? Apa anda tertarik menjadi seorang menteri? Sebelum ...
-
Pernyataan itu di sampaikan Presiden Jokowi dihadapan seputar 2. 000 anggota Gerakan Mahasiswa Islam Indonesia (PMII) yang tengah merayaka...
-
Membuat dual boot windows 7 dengan windows 8 merupakan pilihan bagi anda yang ingin mencoba windows 8 tanpa harus menghapus OS windo...
-
Pengembangan Kurikulum 2013 dilakukan dalam empat tahap. Pertama, penyusunan kurikulum di lingkungan internal Kemdikbud dengan melibatkan...
0 komentar